State puts Columbia back to work to cover for Kennicott

Posted 12/3/25

The Alaska Marine Highway System has put the Columbia back to work through Dec. 17 to cover for the Kennicott, which has been delayed leaving a Puget Sound shipyard.

The Kennicott had been …

This item is available in full to subscribers.

Please log in to continue

Log in

State puts Columbia back to work to cover for Kennicott

Posted

The Alaska Marine Highway System has put the Columbia back to work through Dec. 17 to cover for the Kennicott, which has been delayed leaving a Puget Sound shipyard.

The Kennicott had been scheduled to start work the first week of December between Bellingham, Washington, and Southeast Alaska, but the state reported last week that the ship would be delayed two weeks coming out of the shipyard where it has been most of the year for a new generator and other repairs.

The Kennicott is now scheduled to leave Bellingham on Friday, Dec. 19, to start its northbound run.

The Alaska Marine Highway System was able this week to obtain U.S. Coast Guard approval to run the Columbia a little longer before its winter overhaul, so as to avoid the loss of mainline ferry service through Southeast.

"The U.S. Coast Guard completed the Columbia’s certificate of inspection on Monday and Tuesday (Dec. 1-2) and approved our extension for the next few weeks so the vessel can cover the Kennicott runs," Danielle Tessen, communications manager for the Alaska Department of Transportation, said Dec. 4.

According to the ferry system's online schedule, the Columbia, after being out of service for two weeks, will go back to work on Sunday, Dec. 7, when it will leave Ketchikan for Wrangell on its northbound run through Southeast.

The schedule shows the Columbia leaving service on Dec. 17, after completing its southbound run from Wrangell to Ketchikan, where it will head to the shipyard for winter work.

The ferry system pulls all of its ships out of service each year, generally one at a time, for maintenance and any needed repairs, requiring tight scheduling with the privately operated shipyard in Ketchikan that handles most of the work.

The Kennicott, which was built in 1998, has been out of service all year for installation of new generators to meet emissions standards and other overhaul and maintenance work.

When workers ran some tests on Nov. 20, they discovered an electrical problem between the power system and switchboard, according to the state. “During testing, the control panel kept incorrectly opening the circuit breakers.”

Finding and fixing the problem extended the ferry’s stay at the shipyard.