After missing work for 10 days for engine repairs, the state ferry Columbia is back in service but only until Nov. 28, when it will head to the shipyard in Ketchikan for annual winter maintenance.

…

This item is available in full to subscribers.

Please log in to continue

Log in

Columbia back at work until Nov. 28, then goes into the shop for winter

Posted

After missing work for 10 days for engine repairs, the state ferry Columbia is back in service but only until Nov. 28, when it will head to the shipyard in Ketchikan for annual winter maintenance.

The Kennicott, which has been tied up since June for lack of crew, will take over the mainline route between Bellingham, Washington, and Southeast on Dec. 2, when it will leave Ketchikan, where it has been parked, and head to Bellingham to start the weekly runs to Alaska.

“It looks like it’s ready to go,” Gabe Strong, spokesman for the Alaska Marine Highway System, said of the Kennicott. “It should be a smooth transfer.”

The week of no service between the Columbia and the Kennicott is due to crew changeover, he said.

While the Columbia is in the yard for winter work, “extra care will be taken looking at the engines,” Strong said on Nov. 12. “Since it’s going to the yard soon anyway … we’ll go through everything.”

The 52-year-old ship, the largest in the fleet, was idle in Ketchikan between Nov. 1 and 11 after engineers determined that one of its 9,000-horsepower diesel engines needed a new piston, which was airfreighted by the German manufacturer and arrived in Alaska on Nov. 10.

The piston weighed about 350 pounds, Strong said. He did not have a cost for the part or air freight charges.

The part was delayed at the Seattle-Tacoma International Airport when it failed to pass smoothly through U.S. Customs, he said, noting that the ferry system sent someone to Seattle to help usher the piston through the process.

Repairs went quickly after the part arrived and the ship went back to work for its weekly voyage through Southeast.

“We’re just trying to get to all the ports and people waiting,” Strong said.

To get to all the communities and accommodate the delayed start for its last two weeks of work, the Columbia will call on Wrangell southbound the mornings of Nov. 18 and 25, and northbound the evenings of Nov. 20 and 27, a change from the normal schedule.

When the Kennicott takes over, it will resume the usual schedule of a northbound stop in Wrangell on Sundays and southbound on Wednesdays.

While the Columbia was out of service in Ketchikan, the ferry system allowed the several dozen passengers to remain on the ship, with free room and board. Strong said the system paid refunds to anyone who left and made other travel plans.

Just 34 passengers remained aboard when the ship left Ketchikan on Nov. 11, he said, about half the number who were on board when the ship was scheduled to leave Ketchikan on Nov. 1.